On Friday, 28 March 2025 the government assumed a Caretaker role. Some consultations have been deactivated until further notice, in accordance with the Guidance on Caretaker Conventions.

Overview

Public consultation on Mosman Council’s application for a proposed new amenities building and associated works at Middle Head Oval was open from 28 June to 23 August 2024. The public comment period has now closed.

A total of 233 unique submissions were reviewed. 197 submissions have been made publicly available below.

Read published submissions.

The Harbour Trust has determined the application and granted the applicant a permit with the following key conditions:

  • The proposed demolition of the amenities building and construction of a replacement in a new location is approved.

  • The proposed open-sided shelter is not approved.

  • The proposed vehicle layover bay is not approved – in its stead new vehicle drop-off/pick-up arrangements must be provided in the adjacent Car Park 2.

  • The proposed landscaped area must be re-designed in close consultation with the Harbour Trust to ensure a unified design across the precinct, that minimises hard stand areas and provides shade trees for park users.

The Consultation Outcomes Report and Planning Permit and Conditions can be found on the Harbour Trust website.

To stay up to date, join our mailing list.

Consultation Documents

Please note the majority of documents below are technical in nature, therefore not all of them are available in an accessible format. If you require assistance, please contact the Harbour Trust via: planning@harbourtrust.gov.au

Revised documents

Letter to Trust Mosman Council 23 July 2024 Middle Head Oval amenities building [PDF 123KB]

Middle Head Oval Amenities_Summary Brochure (revised) [PDF 611KB]

Middle Head Oval Amenities_Summary Brochure_word (revised) [DOCX 4.3MB]

Planning Statement_Middle Head Oval amenities building (revised) [PDF 3.67MB]

Heritage Report Middle Head Oval amenities building (revised) [PDF 5.6MB]

Design Statement_Middle Head Oval amenities building (revised) [PDF 14.7MB]

Access Capability Statement Middle Head Oval amenities building [PDF 142KB]

Acoustic Assessment Middle Head Oval amenities building [PDF 3.35MB]

Arborist Report Middle Head Oval amenities building [PDF 3.39 MB]

Architectural Plans [PDF 20MB]

BCA Audit Middle Head Oval amenities building [PDF 1.17MB]

BCA design assessment report Middle Head Oval amenities building [PDF 567KB]

Bushfire Report Middle Head Oval amenities building [PDF 2.23MB]

Cost Plan_Middle Head Oval amenities building [PDF 3MB]

Ecology Report_Middle Head Oval amenities building [PDF 4MB]

Hazardous Materials pre demo assessment_Middle Head Oval amenities building [PDF 2.14MB]

Landscape Report Middle Head Oval amenities building [PDF 10.9MB]

Lighting Report Middle Head Oval amenities building [PDF 9.6MB]

Prelim Site Investigation Middle Head Oval amenities building [PDF 21.3MB]

Stormwater Middle Head Oval amenities building [PDF 2.36MB]

Survey Middle Head Oval amenities building [PDF 1.13MB]

Traffic Middle Head Oval amenities building [PDF 3.24MB]

Waste C&D Middle Head Oval amenities building [PDF 1.17MB]

Waste OWMP Middle Head Oval amenities building [PDF 2.04MB]

Current stage

  • Submissions opened (AEST)
    closed

    28 June 2024 (AEST)

  • Revised information added to consultation 26 July 2024 (AEST)
    closed
  • Submissions closed
    closed

    5pm, 23 August 2024 (AEST)

  • Assessment of application including review of public submissions and feedback
    closed
  • Application determined 28 November 2024
    closed

Upcoming stages

  • Landscaping re-designed, Construction approval granted
    pending
  • Demolition / construction commences
    pending
Contact
Sydney Harbour Federation Trust